14.0 INSTALLATION CHECKLIST

Installation
 1. If operating on Propane Gas, convert boiler using the applicable Natural Gas to LP Conversion
Instructions.
 2. Locate the boiler in accordance with Section 3.0 of this manual.
 3. Install the Vent/Air-inlet piping in accordance with Sections 4.0 and 5.0 of this manual. Ensure all
joints are secured and cemented properly. Perform the Mandatory Pre-commissioning Procedure for
Plastic Venting in Section 4.0.
 4. Connect the condensate trap and drain in accordance with Section 6.0 of this manual.
 5. Connect the gas supply in accordance with Section 7.0 of this manual.
 6. Install the plumbing in accordance with this manual. Flush/cleanse the internals of the heating system.
Treat system water with Fernox F1 Protector when needed.
 7. Connect field wiring in accordance with Section 12.0 of this manual.
 8. Advise home/building owner of their responsibilities with respect to maintaining the boiler.
The building owner is responsible for keeping the Vent/Air-inlet termination free of snow,
ice, or other potential blockages and for scheduling boiler routine maintenance as
described in the next section. Failure to properly maintain the boiler may result in serious injury or death.
Start-up
Allow primers/cements to cure for 8 hours prior to Start-up. If curing time is less than 8
hours, first perform Steps 2 through 6 of Mandatory Pre-commissioning Procedure for
Plastic Venting in Section 4.0. Failure to follow these instructions can result in explosion,
serious injury or death.
 1. Turn gas shut-off valve to the ON position.
 2. Turn Power on to the boiler.
 3. Set Controller to the desired settings.
 4. Turn thermostat up, Ignition will occur.
Operational Checklist
 1. System is free of gas leaks.
 2. System is free of water leaks.
 3. Water pressure is maintained above 15 PSI.
 4. All air is purged from the heating system piping.
 5. Ensure proper water flow rate; unit must not kettle, bang, hiss or flash the water to steam.
 6. Ensure gas line pressure is in accordance with Section 9.0.
 7. System is free of combustion leaks.
 8. Unit must operate smoothly.
 9. Ensure the flue gas combustion readings are within the tolerances listed in Table 9-1.
 10. Each ignition must be smooth.
 11. Verify that all condensate lines are clean and drain freely.
Before Leaving
 1. Seal the Line Pressure Test Port fitting on the inlet flange of the gas valve;, test for leaks. See Section 9.0.
 2. Install flue gas test port plug and test for leaks, see Section 9.0.
 3. Allow the boiler to complete at least one heating cycle, or to operate for at least 15 minutes.
 4. Always verify proper operation after servicing.
Instructions to Installing Contractor
 1. Ensure that the customer receives the Warranty Documentation included with the installation manual.
 2. Leave the manual with the customer so they know when to call for annual maintenance and inspection.
This boiler must have water flowing through it whenever the burner is firing. Failure to
comply may damage the unit, void the warranty, and cause serious injury or death.
Allowing the boiler to operate with a dirty combustion chamber will adversely affect its
operation and void the warranty. Failure to clean the heat exchanger on a frequency that
matches the need of the application may result in fire, property damage, or death.