Operation; First Commissioning - Parker Parkrimp 2 – 83CE-083U Instruction Manual

Table of Contents

Advertisement

Hose Crimper Machine Parkrimp

Operation

Operation
5
Operation
5.1

First commissioning

Figure 5-1 Mounting the
guard hood
Figure 5-2 Oil
Figure 5-3 Level indicator
Figure 5-4 Direction of rota-
tion of motor
2
®
 Remove the transport lug.
 Mount the guard hood using the four screws in the fastening
holes.
 Fill in 40 litres of hydraulic oil HLP 46 DIN 51524 (5) – the oil
level is then in the centre of the level indicator.
 Connect the plant to the power supply.
 Check the direction of rotation of the motor – if necessary reverse
two phases.
 Ventilate the plant – move the pusher several times up and down.
5-1
5-1
Bulletin 4480-T12/UK