Commissioning - Nice RB600 Instructions And Warnings For Installation And Use

For sliding gates
Table of Contents

Advertisement

Run the test as follows:
01.
Ensure that all specifications in the "WARNINGS" chapter have been strictly observed
02.
Release the gearmotor and verify whether it is possible to manually move the gate in both directions (open and close) with a force no
greater than the value corresponding to the usage limits shown in Table 1
03.
Lock the gearmotor
04.
Using the key switch, control key or radio transmitter, test the opening and closing of the gate and make sure that it moves in the in-
tended direction
05.
The test should be carried out several times to verify that the gate moves smoothly, that there are no points of excessive friction and
that there are no defects in the assembly or adjustment
06.
Verify the correct operation of each safety device present in the system (photocells, sensitive edges, etc.)
07.
Check the operation of the photocells and any interference with other devices:
1 - pass a cylinder with 5 cm diameter and 30 cm length along the optical axis, first close to the TX then to the RX
2 - check that the photocells intervene in any condition, switching from active status to alarm status and vice-versa
3 - check that the photocell's intervention determines the intended response of the control unit: for example, it causes the movement
to invert during the closing manoeuvre
4 - Whenever a device intervenes, the "BLUEBUS" LED on the control unit must flash 2 times more quickly, confirming that the control
unit recognises the event
08.
If the dangerous situations caused by the gate's movement have been safeguarded by limiting the impact force, the installer must
measure the impact force according to the EN 12453 standard
If the "Speed" adjustment and "Motor Force" control are used to assist the system in reducing the impact force, try to find the adjust-
ments that provide the best results

6.2 - Commissioning

Commissioning can only take place after all testing phases have been terminated successfully (Paragraph 6.1).
Partial or "makeshift" commissioning is strictly prohibited.
01.
Prepare and store (for at least 10 years) the automation's technical documentation. This must include at least: an assembly drawing
of the automation, a wiring diagram, analysis of risks and relative solutions adopted, manufacturer's declaration of conformity for all
devices installed (for ROBUS use the annexed CE Declaration of Conformity); a copy of the automation system instruction manual and
maintenance schedule
02.
Permanently affix to the gate a label or plate containing instruc-
tions on how to manually release the gearmotor
03.
Using the key selector or transmitter, test the opening and closing of the gate and make sure that it moves in the intended direction
04.
Fill in the declaration of conformity of the automation and hand it to the owner
05.
Hand over to the owner the "User Manual" (pull-out insert)
06.
Prepare and hand to the owner the maintenance schedule of the automation
07.
The force adjustment is an important safety factor and must be done with the utmost care by an qualified technicians. Important! -
Adjust the force sufficiently to enable the gate to move as intended; higher force values to those necessary for moving the gate can
cause injury to animals and persons or damage to property if the gate collides with an obstacle
08.
Before commissioning the gate, inform the owner adequately and in writing about the attendant residual risks