5.5 CHECKING THE GATE MOVEMENT

Once the leaf length has been learned, it is advisable to carry
out a few manoeuvres in order to verify that the gate moves
properly.
24
To do this:
press the [Open
1.
p
the gate opens regularly without any variations in speed;
the leaf must only slow down when it is between 70 cm
and 50 cm from the opening limit switch and then stop at
2–3 cm from the opening mechanical stop when the limit
switch triggers
press the [Close
2.
q
the gate closes regularly without any variations in speed;
the leaf must only slow down when it is between 70 cm
and 50 cm from the closing limit switch and then stop at
2–3 cm from the closing mechanical stop when the limit
switch triggers
during the manoeuvre, check that the warning light flashes
3.
with 0.5 s on/0.5 s off intervals. If present, also check that
the indicator connected to the OGI terminal flashes: slow
during the opening movement, fast during the closing
movement
open and close the gate several times to make sure that
4.
there are no points of excessive friction and that there are
no defects in the assembly or adjustments
check that the gearmotor, rack and limit switch brackets
5.
are solid, stable and suitably resistant even during sudden
gate acceleration or slowdown movements.

5.6 CONNECTING OTHER DEVICES

If the user needs to power external devices, such as a proximity
reader for transponder cards or the light of the key selector
switch, power can be tapped as shown in the figure.
The power supply voltage is 24Vc -30% ÷ +50% with a
maximum available current of 100mA.
25
STOP
1.6AT
] button to open the gate; check that
] button to close the gate; check that
SBS
(-)
(+)
6

TESTING AND COMMISSIONING

These are the most important phases of the automation's
6
TESTING AND COMMISSIONING
construction, as they ensure maximum safety of the system. The
test can also be used to periodically verify the devices making
up the automation.
m
Testing and commissioning of the automation must
be performed by skilled and qualified personnel,
who are responsible for the tests required to
verify the solutions adopted according to the risks
present, and for ensuring that all legal provisions,
standards and regulations are met, in particular
all the requirements of the EN 12445 standard,
which defines the test methods for checking gate
automations.
The additional devices must undergo specific testing, both in
terms of their functions and their proper interaction with the
control unit. Refer to the instruction manuals of the individual
devices.

6.1 TESTING

To run the test:
verify that all the instructions stated in the "GENERAL
1.
SAFETY WARNINGS AND PRECAUTIONS" chapter
have been strictly observed
2.
unlock the gearmotor as indicated in the "Manually
unlocking and locking the gearmotor" paragraph
make sure that the leaf can be moved manually during
3.
both the opening and closing phases with a force not
exceeding 390N (roughly 40 kg)
lock the gearmotor
4.
using the control devices (transmitter, control button,
5.
key selector, etc.), test the gate's opening, closing and
stoppage movements to make sure that the leaves move
as intended. Several tests should be carried out to assess
the movement of the leaves and detect any defects in
the installation and adjustment, besides any points of
excessive friction
check, one-by-one, that all safety devices mounted on the
6.
system (photocells, sensitive edges, etc.) work properly.
Each time a device intervenes, the "Bluebus" LED on
the control unit will emit two faster flashes to confirm the
recognition
7.
if potentially dangerous situations due to the movement
of the leaves have been prevented by limiting the impact
force, the latter must be measured according to the EN
12445 standard and, if the "motor force" control is used to
aid the system in reducing the impact force, it is necessary
to test various adjustments to find the one that gives the
best results.

6.2 COMMISSIONING

a
Commissioning can only be performed after all
testing phases have been successfully completed.
a
Before commissioning the automation, ensure that
the owner is properly informed of all residual risks
and hazards.
a
The gate cannot be commissioned partially or under
"temporary" conditions.