1. Construct the wood framing, ensure inside dimensions are 53"W x 45-
1/2"H as shown below.
45-1/2"
2. Bend both side nailing strips from the side of the appliance until
positioned as shown below.
Determine the overall combined thickness of the non-combustible board
+ inished material being used. The nailing strips can be adjusted up to
3-1/4".
3. Adjust the nailing strips by loosening 2 screws on each nailing strip -
adjust and retighten screws.
4. Attach both vertical studs and secure using 6 screws (2 at bottom, 2 at
top and 2 on sides) as shown.
NOTE: Ensure the lat side of the steel stud is facing the wood framing.
Regency Horizon ® HZ40E-10 Gas Fireplace
14 |
OPTIONAL FRAMING KIT
Framing kit parts
Nailing Strips
(258-025)Flat side out
5. Secure horizontal steel header stud with 2 screws per side as per
diagram.
Header stud
6. Slide the unit into position. Hook up gas, venting, electrical and fan (if
purchased) prior to installing the remaining steel studs.
7. Secure the large horizontal steel stud as shown with 2 screws per side.
8. Secure 2 horizontal studs on the lower side of the appliance with 2
screws per side for each stud as shown.
Large stud
(258-028)
Horizontal
studs
(258-026)
9. Secure 2 vertical studs on either side of the appliance with 4 screws per
side stud as shown.
Vertical studs
(258-027)
(258-026)