Performance Tests and Adjustments
Figure 2-7
5 Download the Wideband Power Sensor Zero Set Verification Utility from the
6 Go through the readme file.
7 Establish a GPIB connection between the signal generator, power meter, and
8 Download and install Keysight VEE Pro Runtime 9.0 or above.
9 The power meter (N1911/2A) and the signal generator (E4438C) must be
10 Run the Wideband Power Sensor Zero Set Verification Utility.
36
Zero set performance test in system level setup
E4438C
link below.
http://www.keysight.com/main/
redirector.jspx?action=ref&cname=EDITORIAL&ckey=1956605&lc=eng&cc=US
&nfr=-536902922.536894476
the PC by using the USB/GPIB interface and a GPIB cable.
added to the Instrument Manager.
Go to Start > Program > Keysight VEE Pro 9.0 or above Runtime Config > IO
Configuration. Select Find to find the connected instrument and Save to save
the configuration.
Keysight N1921A and N1922A Operating and Service Guide
DUT
Power meter