Termination Requirements

!
Venting terminals shall not be recessed into a wall or siding.
A
Minimum 9" (229mm) clearance from any door or window
B
Minimum 12" (305mm) above any grade, veranda, porch, deck or balcony
C
Minimum 3-3/8" (86mm) from outside corner walls
NOTE: Clearance in accordance with local installation codes and the requirements
of the gas supplier.
D
Minimum 12" (305mm) from inside corner walls
NOTE: Clearance in accordance with local installation codes and the requirements
of the gas supplier.
E
Minimum 11" (279mm) clearance below unventilated soffits or roof surfaces
Minimum 18" (457mm) clearance below ventilated soffits
Minimum 6" (152mm) clearance below roof eaves
NOTE: Vinyl surfaces require 24" (610mm)
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.
F
Minimum 12" (305mm) clearance below a veranda, porch, deck or balcony
NOTE: Permitted only if veranda, porch, deck, or balcony is fully open on a minumum of two sides beneath the floor.
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.
G
Minimum 48" (1219mm) clearance from any adjacent building
H
Minimum 84" (2134mm) clearance above any grade when adjacent to public walkways or driveways
NOTE: may not be used over a walkway or driveway shared by an adjacent building
I
Minimum 9" (229mm) clearance to any nonmechanical air supply inlet to the building or the combustion air inlet to any
other appliance.
J
Minimum 36" (914mm) clearance above any mechanical air supply inlet if within 10' (3M) horizontally
K
Minimum 36" (914mm) from the area above the meter/regulator (vent outlet) - this extends 15' (4.5M) above the regulator
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.
L
Minimum 36" (914mm) from the meter/regulator (vent outlet)
NOTE: Clearance in accordance with local installation codes and the requirements of the gas supplier.
M
Minimum 12" (305mm) above the roof line (for vertical terminations)
N
Minimum 24" (610mm) horizontal clearance to any surface (such as an exterior wall) – for vertical terminations
G
NOTE: Measure clearances to the nearest edge of the exhaust hood.
Use the vinyl siding standoff when installing on an exterior with vinyl siding.
Vent termination must not be located where it will become plugged by snow or other material
© Travis Industries
Installation
(for qualified installers only)
E
N
A
F
D
4090507
M
E
K
I
C
L
B
Roof
Surface
Roof
Eaves
11" Min.
(279mm)
6" Min.
(152mm)
E
A
J
H
100-01217_000