Install the GPU-enabled riser cage option.
15.
Slide the retention clips to the locked position.
16.
Install the access panel (on page 26).
17.
Slide the server into the rack.
18.
Connect each power cord to the server.
19.
Connect each power cord to the power source.
20.
Power up the server (on page 24).
21.
Eight-bay SFF front drive cage option for bay 1
To install the component:
Power down the server (on page 24).
1.
Remove all power:
2.
Hardware options installation 68