6. Remove the M6×25 hexagonal bolts, spring washers and flat washers, which fix the plate support and
load cell in two locations both above and under.
7. Fix a new load cell and fix in four locations on the upper and lower plate support with flat washers,
spring washers, and M6×25 hexagonal bolts order.
The direction of load cell installation should be carried out on the lower plate support on the cell cable
side.
8. Confirm whether each cell limit space in the 8-location set screws is within a specified value.
Adjust by turning the set screws to the regulations value, and apply the screw lock agent if differing
from a specified value.
9. Start the test mode, and perform the C3 mode span adjustment.