Installation

Installation

Mechanical

Only qualified contractors experienced with mechanical installations and the hazards
associated with them should perform the following instructions.
1
Ensure all power is disconnected.
2
Prepare the site (see Site Preparation, p. 10).
3
Pull and label wires for power and control.
4
Bolt operator in place (see Figure 8). Use washers to level operator.
5
Attach Crank arm (see Figure 9).
Figure 8
6
Attach gate bracket at fence 31" from top of pad (see Figure 10) and
approximately 36" from gate hinge.
Gate
5"
31"
+/-
½
Doc 01-G0181
Rev A
Figure 9
01-G0181F8
Figure 10
01-G0181F9