Completing the adjustments
- Switch the boiler OFF and close the test ports and hose
nipples; check for leaks.
- Fit the casing.
Test run
- Reset the MCBs.
- pen the gas tap.
- Switch ON the boiler.
- Set the program selector to emissions test mode.
Carrying out a ventilation test
Check LAF for soundness, if the CO
0.2%.
Flue gas test
Re-adjust the CO
content, if required
2
(see next page)
48
Maintenance
value >
2
Emissions test mode position