Figure 1.17 Power/Signal Connections - Hydrogen; Figure 1.18 Lc1000/Lc1500 Generator Run - Bard D36A2P/BLD.10304 Installation And Service Instructions Manual

Replacement parts manual dc free cooling unit system two (2) d-series dual-tec™ wall-mounted package one (1) bard-linktm plc lead/lag controller controller models lc1000-100/bld.10293, lc1500-100/bld.10291
Table of Contents

Advertisement

Power and Signal Connections for Bard-Supplied Hydrogen Detector (If Applicable)
-24VDC
Return
Signal
-24VDC
-24VDC
+24VDC
+24VDC
LC1000-100 and LC1500-100 Series Generator Run
-24VDC Return Signal
-24VDC
FIGURE 1.17
1.
Using minimum 18 gauge, non-shielded wire, supply the
new hydrogen detector with 24VDC from terminals 3 and 4
of the PLC controller.
2.
Route a jumper wire from the -24VDC terminal on the new
hydrogen detector to the common terminal of the on-board
2% relay.
3.
From the normally closed contact of the relay, return the
-24VDC signal to terminal #5 of the PLC controller.
FIGURE 1.18
1.
If there is a generator on site, remove the factory-
installed jumper on Terminals #9 and #10. Using
minimum 18 gauge, non-shielded wire, supply the
common terminal on the existing generator relay with
-24VDC from terminal #9 on the PLC controller.
2.
From the normally closed contact of the relay, return
COM
NC
the -24VDC signal to terminal #10 of the PLC
controller.
See Terminal Block Index
on page 33
Manual 2100-620A
Page
25 of 107