System inspection and maintenance
Additional maintenance work as-needed
1.
Shut down the heating system
2.
Remove and clean heat exchanger baffles
3.
Clean the flue gas passages (heating surfaces) and flue gas baffles
4.
Clean the combustion chamber
5.
Clean the draft diverter
6.
Insert the flue gas baffles
7.
Check gaskets/sealant ropes on the burner and burner door and replace if
required (see burner documentation)
8.
Commissioning the heating system
9.
Record the final checks of the maintenance work, incl. measurements and
test results
10.
Check safe and proper operation
Confirm professional inspection
Date:____________
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Company stamp/signature
44
Page
38
39
40
40
40
40
35
Date:____________
Company stamp/signature
Date:____________
Company stamp/signature
Date:____________
Company stamp/signature
Logano G515 – 6 720 647 208 (2014/09)
Date:____________
Company stamp/signature
Date:____________
Company stamp/signature