8
Placing the Boiler in Operation
8.11 Detailed Start-up Procedure
Check off performed start-up steps, sign and date.
Start-up Procedure
1.
Filling of system and check for leaks
2.
Set operating pressure
Vent heating system
Check operation of relief valve
Pre-set expansion tank pressure (
structions)
3.
Check combustion air and venting system
4.
Check position of flue baffles
5.
Turn on control (
Refer to control Service Manual)
6.
Turn on burner (
Refer to burner Service Manual)
7.
Measure stack temperature (Adjust if needed)
8.
Check manual reset high limit (STB)
9.
Adjust control settings based on requirements (
Manual)
10. Inform end user and hand over instructions
Confirm start-up procedure
NOTICE
Always inform your customer regard-
ing proper fuel source and record in
Operating Manual.
46
see expansion tank manufacturer in-
Refer to control Service
Logano G125 BE - Specifications subject to change without notice.
Page
Value Measured
33
__________ psi
39
__________ psi
40
41
41
42
__________ °F
44
Company stamp/signature/date
Comments