Installing The Optional Rps System - 3Com SuperStack II PathBuilder S330 Reference Manual

Wan access switches
Hide thumbs Also See for SuperStack II PathBuilder S330:
Table of Contents

Advertisement

26
C
2: I
HAPTER
NSTALLATION
To connect AC or DC power:
WARNING: Before handling AC/DC power leads, disconnect all power supply
cords and always have a partner close by who is familiar with first aid for electrical
shock.
CAUTION: CENTRALIZED 48VDC UNITS -To be installed only in Restricted Access
Areas (dedicated equipment rooms, equipment closets, etc.) in accordance with
Articles 110-16 or 110-17, and 110-18 of the National Electrical Code, ANSI/NFPA
No.70.
1 Turn off the AC/DC power source and connect the AC/DC leads to the front of the
shelf. Dress the leads to the rack, leaving a service loop.
2 Turn on AC/DC power and verify that the POWER indicator on the power supply is
on and that the fans are running. Figure 20 shows the shelf fill for the AC/DC
power application.
Figure 20 Shelf Fill for AC/DC Power Application
AC Units Only:
AC Power Connector / Fuse Holder
DC Units Only:
DC Power Connector
+
GND

Installing the Optional RPS System

The PathBuilder S330/S310 switch also supports the SuperStack II Redundant
Power Supply (RPS). Figure 20 above shows the location of the RPS. Only connect
a 3Com RPS, option 3C16073, to this socket. For details, follow the installation
instructions in the guide accompanying the RPS.
Redundant Power Supply (RPS) Connector
Vent
Vent

Advertisement

Table of Contents
loading

This manual is also suitable for:

Superstack ii pathbuilder s310

Table of Contents