ES45T-T-1
The ES45T-T-1 reflector is composed of six precision-formed panels designed for accu-
Reflector
rate strength, and ensures a reliable surface contour that provides exceptional operating
characteristics in C-, X- or Ku-frequency bands.
Step 1
Reflector should be assembled on a clear, flat area in front of the foundation pad. Clear
debris from area and place plastic sheeting from packing crate as shown in Figure 56.
Step 2
Arrange diameter setting band assembly (P/N 49612) and temporary supports as shown
in Figure 54.
Tighten ¼-20 hardware at center connection until snug
Reflector should be assembled in front of foundation pad with bottom of reflector 3 ft.
from pad
Temporary supports should be 6-8 in. high
Tie three string levels to opposing blocks across diameter of circle
Adjust supports with shims until strings are level and lightly touch at center of circle
Once supports are level, remove strings
Move supports 12 in. radially away from circle, carefully maintaining orientation and
height for later reuse