Step 16
Connect U-bracket (P/N 49704) to appropriate connection plate.
Use A-325 ½ x 1-½ in. bolts, flatwashers and nuts. (see page 12)
Step 17
Determine required length of azimuth strut to nearest degree increment of desired
azimuth setting as specified in the Elevation and Azimuth Adjustments Section. Adjust
azimuth setting by withdrawing secondary strut to achieve necessary length. Install four
½ in. set screws and securely tighten as demonstrated in Figure 19.
Step 18
Connect one end of azimuth strut (P/N 49767) to connection plate with U-bracket (P/N
49704) as indicated in Figure 18.
Use ¾ x 4-½ in. bolts, lockwashers and nuts
Securely tighten all A-325 ground mount hardware except the fine adjustment hardware
per A-325 tensioning procedure (see page 12).
Step 19
The tripod ground mount assembly is now completed with the necessary operational
essentials. All ground mount options have separate instructional bulletins located in the
parts kit that contain the option.The next step in the installation process is the reflector
assembly. Proceed to the appropriate section for the type of reflector you are installing.
Figure 18
Figure 19
21
Installation Procedures

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents