NOTE:
the exterior of the building. Adjust the termination cap to
WARNING
is pointing up.
Attach the termination cap with the four wood screws provided.
Before attachment of the termination, run a bead of silicone sealant
rated above 250°F on its outside edge too, so as to make a seal
to the exterior wall.
NOTE: Wood screws can and should be replaced with appropriate
fasteners for use on stucco, brick, concrete or other types
of siding.
CAUTION:
that could become discolored or warp), it is necessary to install a
vinyl siding standoff.
The vinyl siding standoff will be installed between the vent termination
and the exterior wall. (See Figure 44) This horizontal vent termination
will exist between the wall and the termination cap.
29354-1-1012

HORIZONTAL TERMINATION

Figure 44
For installations requiring a vertical rise on the exterior of the
building, 14-inch and 36-inch tall Snorkel Terminations, as shown in
Figure 45 are available. Follow the same installation procedures as
used for standard Horizontal Terminations. If the Snorkel Termination
must be installed below grade, (i.e. basement application), proper
drainage must be provided to prevent water from entering the
Snorkel Termination. Refer to Figure 46. Do not attempt to enclose
the Snorkel within the wall or any other type of enclosure.
Figure 45
Figure 46