The floor anchor brackets, shipped separately from the UPS and battery
cabinet, should be attached inside the lower front and rear edges of the
cabinet before installing power and battery modules and before making
connections to the intended power source.
Use mounting hardware supplied with the floor anchor kit to attach the
brackets to the UPS or external battery cabinet (see Figure 12). The
customer is responsible for specifying and supplying floor mounting
bolts.
+
Powerware
9170
UPS User's Guide
®
Mounting Centers for 5/16I (8-mm) Floor Bolts
Dimension (see Figure 12)
A
B (3- and 6-slot cabinets)
B (9- and 12-slot cabinets)
B
Figure 12. Floor Anchor Brackets Bolted to UPS Cabinet
Rev B www.powerware.com
S
Installation Setup
Measurement
14.5I (36.8 cm)
30.25I (76.8 cm)
34.25I (87 cm)
Floor Anchor
Bracket
A
15

Advertisement

Table of Contents
loading

Table of Contents