PARALLEL INSTALLATION
7.
8.
9.
16
EATON Powerware
Punch holes for the conduit (AC input, each UPS output, and load
connection) using a Greenlee
Verify that the parallel bypass breaker is in the OFF position (see
Figure 8).
Mount the parallel tie cabinet to the wall and install the conduit.
Figure 8. Parallel Bypass Breaker
®
9155 Parallel UPS (8–15 kVA) User's Guide
punch or similar device.
®
S
164201592 Rev C www.powerware.com