8
Actions
Fit the cover on the external connection box (see fig. 54).
Fit the casing.
Switch on the power supply of the heating system on the circuit
breaker.
Set the main switch on the BC10 to "1" (On).
8.1.24 Bleed the gas supply pipe
Switch off the power supply of the heating system on the circuit
breaker.
Set the main switch on the BC10 to "0" (Off).
Remove the casing.
Close the gas shut-off valve (see fig. 56, pos. 1).
Open the screw plug on the testing nipple for the inlet gas pres-
sure and for purging (fig. 55) by two turns and install a hose.
Open slowly the gas shut-off valve.
Run the gas that flows out through a water bath.
Close the gas shut-off valve when no more air escapes.
Remove the hose and tighten the screw plug again.
Carefully open the gas shut-off valve (see fig. 56, pos. 2).
Check the testing nipple for leaks.
Fit the casing.
Switch on the power supply of the heating system on the circuit
breaker.
Set the main switch on the BC10 to "1" (On).
106
Logamax plus GB142-24/30/45/60 - We reserve the right to make any changes due to technical modifications!
fig. 54
Installing the cover of the connection box
fig. 55
Bleeding the gas supply pipe