8
Actions
NOTICE!
Carry out all start-up activities according to the
Installation and Servicing Instructions and
complete the start-up report.
You must also check all gaskets and seals affected by the replace-
ment activities during the tightness test carried out in operating
conditions!
Fit the casing.
8.1.23 Checking the control unit; connections to the boiler
If an On/Off thermostat is used and the boiler does not react to
a heat request:
Switch off the power supply of the heating system on the circuit
breaker.
Set the main switch on the BC10 to "0" (Off).
Remove the casing.
Remove the cover from the connection box (see fig. 50).
Use a jumper wire to create a bridging circuit between the two
"WA" contacts (see fig. 53, pos. 3).
Connect the heating system to the power supply, insert the
main fuse or switch on the circuit breaker.
Set the main switch on the BC10 to "1" (On).
If the boiler switches to heating mode (operating code [-/h/\| )
after some time, the cause of the fault must be outside the
boiler.
Switch off the power supply of the heating system on the circuit
breaker.
Set the main switch on the BC10 to "0" (Off). See page 9 „Menu
structure of the BC10 basic controller".
Remove the bridge between the two "WA" contacts (see fig. 53,
pos. 3).
Connect the On/Off thermostat directly to the two "WA"
contacts of the boiler using a short cable (see fig. 53, pos. 3).
Switch on the power supply of the heating system on the circuit
breaker.
Set the main switch on the BC10 to "1" (On).
Set the On/Off thermostat to the request position.
If the boiler switches to heating operation (operating code
[-/h/\| ) after some time, the fault is caused by the cable
between the On/Off thermostat and the boiler.
104
Logamax plus GB142-24/30/45/60 - We reserve the right to make any changes due to technical modifications!
fig. 49
Gas shut-off valve closed (1), gas shut-off valve
open (2)
fig. 50
Removing the cover from the connection box
fig. 51
Installing the cover of the connection box