14.1

Operation Types

The operation types are summarized below.
Operation
Complete Shutdown
Float / Equalize Charge
Protection Charge
Startup
Stop
Switch Power Supply
14.2

Pre-operational Check

Perform the pre-operational check before operating the UPS.
Before operating the UPS:
1. Make sure all covers/panels are in place and secured.
2. Make sure the temperature in the UPS/Battery room is within specified limits.
3. Before starting the UPS, check the power source to make sure AC input power is on.
4. Make sure battery breaker's auxiliary A-contact is connected to the terminal block TB1.
62
TABLE 14.1 OPERATION TYPES
Description
Turn off the control power supply. Shut down the UPS
completely.
Changing the battery recharge mode between float charge and
equalize charge.
Automatic recharge mode transition from protection charge to
float charge.
Starting up and operating the UPS.
Stop the inverter and chopper/charger.
Switching power supply source between UPS and Bypass.
CAUTION