3-3. Installation of the sewing machine head

WARNING :
To prevent possible accidents caused by the full of the sewing machine, perform the work by two
persons or more when the machine is moved.
A

3-4. Installing the drain receiver and the head support rubber

7
6
6
6
1
4
1
3
6
2
6
8
5
1) Fit the holes of hinges A to the holes of table
and fix as shown in the figure.
In case of the pneumatic type, fix sole-
noid valve installing plate 1 as well.
1) Fix drain receiver 2 in the installing hole of
table 1 with two setscrews 3 .
2) Screw in drain bin 4 to drain receiver 2 .
3) Insert sewing machine drain pipe 5 into drain
bin 4 .
4) Insert head support rubbers 6 to machine bed 7 .
5) Bundle the cables with clip bands 8 as shown
in the figure. (Excluding air tube)
1. Insert drain pipe 5 until it will go
no further so that it does not come
off drain bin 4 when tilting the ma-
chine head.
2. Remove the tape fixing drain pipe
5 .
6
– 5 –

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ip-420Ams-210en

Table of Contents