UPS MAINTENANCE

Testing New Batteries

72
Eaton
®
9130 UPS (700–3000 VA) User's Guide
5. For each cable retention clip removed, rotate the clip and install it
under each EBM cable connection using the retained screws.
6. Verify that the EBM connections are tight and that adequate bend
radius and strain relief exist for each cable.
To test new batteries:
1. Plug the UPS into a power outlet for 48 hours to charge the
batteries.
2. Press any button to activate the menu options.
3. Select CONTROL then START BATTERY TEST.
The UPS starts a battery test if the batteries are fully charged, the
UPS is in Normal mode with no active alarms, and the bypass
voltage is acceptable.
During the battery test, the UPS transfers to Battery mode and
discharges the batteries for 25 seconds. The front panel displays
"Battery test running" and the percentage of the test completed.
S