Installation Troubleshooting

Q:
Problem
Water is leaking under the unit.
A:
Solution
A water leak under the unit is most likely caused by a bad
connection in the water supply line. Make sure the water
line's brass fitting is screwed tight to its valve and
threaded correctly. Make sure the fill tube's connection to
the water line is also tight. Check drain line to make sure
it has not been disconnected from drain connection on
back of the unit or disconnected from the drain.
Q:
Problem
The door remains open unless it is pushed closed.
A:
Solution
The hinges should be self-closing when the door is open
approximately 8". If this is not the case, make sure the
closers (at the bottom of the hinge pin) are clean, greased
and installed correctly. Also, re-check leveling from front
to back of the unit and readjust if necessary. Make sure
that pivot plate is installed correctly.
Q:
Problem
The custom overlay door was designed to align with the
rest of the cabinet doors, but the unit has crept forward.
A:
Solution
First, make sure that the electrical cord and water supply
line are not obstructing the installation. If they are not,
there is mostly likely not enough room allowed for the
drain connection on the rear of the unit. You may need to
alter the wall behind the unit to accommodate the drain
connection.
www.U-LineService.com
CLR2060 — Clear Ice Maker
10 Start-Up for the First Time

Initial Start-Up

Once installation and leveling is complete, the unit is
ready for initial start-up and operation. The cycle selector
switch is located in the front grille (see Figure 45).
Figure 45
1. Open the door and remove the cover in front of the
evaporator by gently compressing and pulling
forward. This will enable you to observe the water
flow over the evaporator.
2. Check that the overflow tube is inserted securely into
the water trough.
3. Put the cycle selector switch (in the grille) in the ICE
position (press the switch up). The water fill valve will
energize and fill the water reservoir. The water fill valve
shuts off after approximately 180 seconds (3 minutes).
The compressor begins to operate.
18
Cycle Selector
Switch
02/2005