WIRING THE AC MAINS AND LOADS TO THE PDU

208 or 220 V 3-Phase Wye

Figure 15. Wiring the Mains: 208 or 220 V 3-Phase Wye
The line-to-line voltage must not exceed 240 volts.
Tools for connecting the mains and loads:

1/4-inch flat blade screwdriver for the Mains Disconnect Switch

1/8-inch flat blade screwdriver for the Output Terminal Block
Set the Voltage Selector Switch (S1) on the Control Board to 230V (page 9).
Wiring Loads: Wire line-to-line.
HP E1135C POWER DISTRIBUTION UNIT Rev. C
26
L1
L2
L3
N
1
0
G
T1
T2
T3
N
10A 10A
G
L1 L2 L3
NOTE
MAINS6.WPG