12.4.3 Operation test run

12.4.4 Actuator test run

EBLA04~08E2V3+E23V3 + EDLA04~08E2V3+E23V3
Daikin Altherma 3 M
4P685228-1A – 2022.05
6 To stop the air purge manually:
1 In the menu, go to Stop air purge.
2 Select OK to confirm.
Purpose
Perform test runs on the unit and monitor the leaving water and tank
temperatures to check if the unit is working correctly. The following test runs
should be made:
Heating
Cooling (if applicable)
Tank
To perform an operation test run
Conditions: Make sure all operation is disabled. Go to [C]: Operation and turn off
Space heating/cooling and Tank operation.
1 Set the user permission level to Installer. See
the user permission
2 Go to [A.1]: Commissioning > Operation test run.
3 Select a test from the list. Example: Heating.
4 Select OK to confirm.
Result: The test run starts. It stops automatically when ready
(±30 min).
To stop the test run manually:
1 In the menu, go to Stop test run.
2 Select OK to confirm.
INFORMATION
If the outdoor temperature is outside the range of operation, the unit may NOT
operate or may NOT deliver the required capacity.
To monitor leaving water and tank temperatures
During test run, the correct operation of the unit can be checked by monitoring its
leaving water temperature (heating/cooling mode) and tank temperature
(domestic hot water mode).
To monitor the temperatures:
1 In the menu, go to Sensors.
2 Select the temperature information.
Purpose
Perform an actuator test run to confirm the operation of the different actuators.
For example, when you select Pump, a test run of the pump will start.
4
level" [
 124].