11.4.3 Operation test run

EPRA08~12EAV3+W1 + ETSH/X(B)12P30+50EF
Daikin Altherma 3 H MT ECH₂O
4P663478-1B – 2022.07
To perform an automatic air purge
Conditions: Make sure all operation is disabled. Go to [C]: Operation and turn off
Space heating/cooling and Tank operation.
1 Set the user permission level to Installer. See
the user permission
2 Go to [A.3]: Commissioning > Air purge.
3 In the menu, set Type = Automatic.
4 Select Start air purge.
5 Select OK to confirm.
Result: The air purge starts. It stops automatically when done.
6 To stop the air purge manually:
1 In the menu, go to Stop air purge.
2 Select OK to confirm.
Purpose
Perform test runs on the unit and monitor the leaving water and tank
temperatures to check if the unit is working correctly. The following test runs
should be made:
Heating
Cooling (if applicable)
Tank
To perform an operation test run
Conditions: Make sure all operation is disabled. Go to [C]: Operation and turn off
Space heating/cooling and Tank operation.
1 Set the user permission level to Installer. See
the user permission
2 Go to [A.1]: Commissioning > Operation test run.
3 Select a test from the list. Example: Heating.
4 Select OK to confirm.
Result: The test run starts. It stops automatically when ready
(±30 min).
To stop the test run manually:
1 In the menu, go to Stop test run.
2 Select OK to confirm.
INFORMATION
If the outdoor temperature is outside the range of operation, the unit may NOT
operate or may NOT deliver the required capacity.
4
level" [
 143].
4
level" [
 143].
11
Commissioning
|
"To change
"To change
Installer reference guide
239

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents