Test operation and lighting sequence

It may take approximately two hours of operation for the burn media to achieve their full flame
pattern and glow. During the initial burning in period, some smoke and smell may be experienced.
The appliance should run on the high setting in a well ventilated room until these dissipate. It is
important to check the flame pattern during this time.
Abnormal flame pattern
Abnormal flame performance and/or pattern can indicate
a problem with your fire, such as blocked gas injectors,
or that the burn media has shifted. There are some
warning signs that could indicate a problem.
-
Unusual smell from the appliance
-
Continued difficulty or delay in establishing a flame
-
Flame appears either very short or very long
-
Flame only burns part way across the burner
-
Severe soot building up on the inside of the glass
Important
It is the responsibility of the installer to check that under
normal conditions of the appliance, all flue gases are
exhausted to the outside atmosphere, and that there is
no spillage of combustion gases into the room.
If the appliance cannot be made to perform correctly
please contact Rinnai.

Installation checklist and customer handover

Complete the installation checklist in the customer operation guide, and make
sure you leave the guide with the customer. Take the time to explain to the
customer about the use and care of the unit, and that they understand the
instructions.
26 | Novo freestanding installation guide:13992-A 01-22
Normal flame pattern
Abnormal flame pattern
Soot build up

Advertisement

Table of Contents
loading

This manual is also suitable for:

Novo freestanderRdv2320fnRdv2320fl

Table of Contents