16.3.2 Checking refrigerant piping: General guidelines

16.3.3 Checking refrigerant piping: Setup

RKXYQ5T8+8T7Y1B + RDXYQ5T8+8T7V1B
VRV IV heat pump for indoor installation
4P499898-1B – 2021.12
If there is a possibility of moisture being present in the refrigerant piping (for
example, water may have entered the piping), first carry out the vacuum drying
procedure below until all moisture has been removed.
All piping inside the unit has been factory tested for leaks.
Only field installed refrigerant piping needs to be checked. Therefore, make sure
that all the compressor unit stop valves are firmly closed before performing leak
test or vacuum drying.
NOTICE
Make sure that all (field supplied) field piping valves are OPEN (not compressor unit
stop valves!) before you start leak test and vacuuming.
For more information on the state of the valves, refer to
refrigerant piping:
Setup" [
Connect the vacuum pump through a manifold to the service port of all stop valves
to increase efficiency (refer to
NOTICE
Use a 2-stage vacuum pump with a non-return valve or a solenoid valve that can
evacuate to a gauge pressure of –⁠ 1 00.7 kPa (−⁠ 1 .007 bar)(5 Torr absolute).
NOTICE
Make sure the pump oil does not flow oppositely into the system while the pump is
not working.
NOTICE
Do NOT purge the air with refrigerants. Use a vacuum pump to evacuate the
installation.
The system contains 2 refrigerant circuits:
Circuit 1: Compressor unit → Heat exchanger unit
Circuit 2: Compressor unit → Indoor units
You have to check both circuits (leak test, vacuuming drying). How to check
depends on your available tools:
If you have a manifold...
With refrigerant line
splitters
Without refrigerant line
splitters
(takes twice as long)
Possible connections:
4
 79].
"16.3.3 Checking refrigerant piping:
You can check both circuits at once. To do so, connect
the manifold via the splitters to both circuits, and
check.
You have to check the circuits separately. To do so:
First connect the manifold to circuit 1, and check.
Then connect the manifold to circuit 2, and check.