16.3.5 To perform vacuum drying

16.3.6 To insulate the refrigerant piping

RKXYQ5T8+8T7Y1B + RDXYQ5T8+8T7V1B
VRV IV heat pump for indoor installation
4P499898-1B – 2021.12
2 Discharge all nitrogen gas.
3 Break the vacuum by pressurising with nitrogen gas to a minimum gauge
pressure of 0.2  MPa (2  bar). Never set the gauge pressure higher than the
maximum operation pressure of the unit, i.e. 4.0 MPa (40 bar).
NOTICE
ALWAYS use a recommended bubble test solution from your wholesaler.
NEVER use soap water:
Soap water may cause cracking of components, such as flare nuts or stop valve
caps.
Soap water may contain salt, which absorbs moisture that will freeze when the
piping gets cold.
Soap water contains ammonia which may lead to corrosion of flared joints
(between the brass flare nut and the copper flare).
NOTICE
The connections to the indoor units and to the heat exchanger unit, and all indoor
units and the heat exchanger unit itself should also be leak and vacuum tested. Keep,
if existing, all (field supplied) field valves to the indoor units and to the heat
exchanger unit open as well.
Leak test and vacuum drying should be done before the power supply is set to the
unit. If not, see
information.
To remove all moisture from the system, proceed as follows:
1 Evacuate the system for at least 2 hours to a target vacuum of –⁠ 1 00.7  kPa
(–⁠ 1 .007 bar)(5 Torr absolute).
2 Check that, with the vacuum pump turned off, the target vacuum is
maintained for at least 1 hour.
3 Should you fail to reach the target vacuum within 2 hours or maintain the
vacuum for 1 hour, the system may contain too much moisture. In that case,
break the vacuum by pressurising with nitrogen gas to a gauge pressure of
0.05  MPa (0.5  bar) and repeat steps 1 to 3 until all moisture has been
removed.
4 Depending on whether you want to immediately charge refrigerant through
the refrigerant charge port or first pre-charge a portion of refrigerant through
the liquid line, either open the compressor unit stop valves, or keep them
closed. See
"16.4.4 To charge
INFORMATION
After opening the stop valve, it is possible that the pressure in the refrigerant piping
does NOT increase. This might be caused by e.g. the closed state of the expansion
valve in the compressor unit circuit, but does NOT present any problem for correct
operation of the unit.
After finishing the leak test and vacuum drying, the piping must be insulated. Take
into account the following points:
Make sure to insulate the connection piping and refrigerant branch kits entirely.
"16.3.1  About checking the refrigerant
4
refrigerant" [
 84] for more information.
16
Piping installation
|
piping"  [
4
  78] for more
Installer and user reference guide
81

Advertisement

Table of Contents
loading

Table of Contents