Installing the Application Gateway

Rack Mounting the Application Gateway

Rack Mounting the Application Gateway

Separating the Rail Sections

1
2
6
Application Gateway Hardware Installation Guide
The enclosed rack-mounting kit can be used to install the Application
Gateway in a four-post or two-post rack.
The rack-mounting kit includes two sets of rail assemblies, two rail
mounting brackets, and the mounting screws that you will need to install
the system into the rack. Follow the steps in the order given to complete
the installation process in a minimum amount of time. Please read this
guide in its entirety before you begin the installation.
Each of the rail assemblies consist of two sections: an inner fixed chassis
rail that secures to the server (A) and an outer fixed rack rail that secures
directly to the rack itself (B), as illustrated below. A sliding rail guide
sandwiched between the two should remain attached to the fixed rack rail.
You must separate the A rail from the B rail to begin the installation.
To separate the A and B rails:
Pull the fixed chassis rail (A) out as far as possible — you should hear a
click sound as a locking tab emerges from inside the rail assembly and
locks the inner rail.
Depress the locking tab to pull the inner rail completely out. Do this for
both the left and right side rack rail assemblies.