Ice Build Control

IMPORTANT: The Ice Build control option is only available on machines with PSIO
Software Version 09 and higher.
Ice build control automatically sets the chilled WATER/ BRINE CONTROL POINT of the
machine to a temperature where an ice building operation for thermal storage can be
accomplished.
Note: For ice build control to properly operate, the PIC controls must be placed in CCN mode.
See
Figure 16
The PIC can be configured for ice build operation. Configuration of ice build control is
accomplished through entries in the Config table, Ice Build Setpoint table, and the Ice Build
Time Schedule table.
The Ice Build Time Schedule defines the period during which ice build is active if the ice build
option is ENABLED. If the Ice Build Time Schedule overlaps other schedules defining time, then
the Ice Build Time Schedule shall take priority. During the ice build period, the WATER/BRINE
CONTROL POINT is set to the ICE BUILD SETPOINT for temperature control. The ICE BUILD
RECYCLE OPTION and ICE BUILD TERMINATION entries from a screen in the Config
(configuration) table provide options for machine recycle and termination of ice build cycle,
respectively. Termination of ice build can result from the ENTERING CHILLED WATER/BRINE
and
Figure
17.
Figure 16
and
Figure 17
show how to access each entry.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

19xl

Table of Contents