d. Navigate to System #1 screen then define con-
trol mode, dispense mode, and pump informa-
tion. See page 61.
e. Navigate to System #2 screen then define dis-
pense valve details and other system settings.
See page 61.
f.
Navigate to System #3 screen then define
labels, pressure imbalance, and flow meter
details. See page 62.
g. Navigate to Shots screen then define shots.
See page 59.
h. Navigate to Sequences screen then define
sequences. See page 60.
i.
If desired, navigate to Maintenance screen
then reset counters. See page 62.
11.Perform Flushing procedure,
page 43.
NOTICE
The machine is tested with oil at the factory. Flush
out the oil with a compatible solvent before loading
the machine with material. See Flushing on
page 43.
12.If not already open, open the fluid
inlet ball valves to load the system
with material.
13.Perform System Setup and Cali-
bration procedure, page 29.