Commissioning

20 Commissioning
In this chapter

20.1 Overview: Commissioning

20.2 Precautions when commissioning

20.3 Checklist before commissioning

Installer and user reference guide
74
NOTICE
General commissioning checklist. Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during the
commissioning and hand-over to the user.
20.1
Overview: Commissioning ......................................................................................................................................................
20.2
Precautions when commissioning..........................................................................................................................................
20.3
Checklist before commissioning.............................................................................................................................................
20.4
To perform a test run .............................................................................................................................................................
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
After the installation of the unit, first check the items listed below. Once all checks
are fulfilled, the unit must be closed. Power-up the unit after it is closed.
You read the complete installation and operation instructions, as described in the installer
and user reference guide.
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
74
74
74
75
FAA71+100BUV1B
Split system air conditioner
4P654517-1 – 2021.03

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Faa100buv1b

Table of Contents