Cable Entry In The Protective Cabinet And Eacie Panel - C-TEC EACIE Installation, Maintenance & Operating Manual

Evacuation alert control and indicating equipment
Hide thumbs Also See for EACIE:
Table of Contents

Advertisement

EACIE Evacuation Alert Control and Indicating Equipment
5.4

Cable Entry in the Protective Cabinet and EACIE Panel

Mains wiring should be segregated from extra low voltage field wiring. Leave sufficient tails of at least 1m
inside the panel to ensure straightforward connection of wiring to the panel's terminals.
Important Note: The security of the protective cabinet must not be compromised during installation, e.g. as
result of the cable entry method.
All field cables should be fed through the rear slot / aperture in the protective cabinet (see Photo 1).
Feed cables through the top slot / aperture in the EACIE chassis.
Route the mains supply cable along the left-hand side of the EACIE chassis to the PSU (see Photo 2).
Route the loop cables (and cables to the fault relay – if used) along the right-hand side of the EACIE
chassis to the Main Control PCB (see Photo 3).
Terminate cable screens to the earth bar at the top of the EACIE chassis (see Photo 4).
PHOTO 1: FIELD CABLES FED THROUGH
REAR SLOT IN PROTECTIVE CABINET
PHOTO 3: LOOP CABLES FED THROUGH
TOP SLOT IN EACIE CHASSIS AND ROUTED
TO MAIN CONTROL PCB
Installation and Programming Manual  Approved Document No. DFU5030020 Rev 1  Page 12 of 38
PHOTO 2: MAINS CABLES FED THROUGH
TOP SLOT IN EACIE CHASSIS AND
ROUTED TO PSU
PHOTO 4: CABLES SCREENS TERMINATED
AT EARTH BAR IN EACIE CHASSIS