SECTION 1B

1.1 INSPECTION

A. The Precision Plasmarc System will be shipped in
four separate containers. The power source, the
junction box, the flow control box and the PT-24 torch
components will all have their own containers. Re-
move all packing material and inspect for evidence of
concealed damage which may not have been appar-
ent upon receipt of the four containers. All four
components, the power source, flow control box,
junction box and PT-24 torch are fully assembled.
Immediately notify the carrier of any defects or dam-
age.

UNPACKING/HOISTING

B. Check each container for any loose parts prior to
disposing of shipping materials.
C. Check air louvers on the power source and junction
box and any other opening to ensure that any obstruc-
tions are removed.

1.2 HOISTING

The power source is equipped with one lifting eye that
enables the unit to be hoisted.