Figure 5-3 Diagram Of Input/Output Bus Bars And Terminal Blocks (750Kva) - Toshiba G2020 Series Installation And Operation Manual

480/480 v 500kva/750kva
Hide thumbs Also See for G2020 Series:
Table of Contents

Advertisement

Location of bus bars and terminal blocks (Bottom/Top/Left Side entry)
AC Input
A , B , C
Bypass Input
A 40 , B 40 , C 40
AC Output
A 50 , B 50 , C 50
DC Input
BP , BN
Grounding Bar
( not shown )
G2020 Series UPS Installation and Operation Manual – 94861-004
D=33.5" (850mm)
81.6" (2073)
16.5" (420)

Figure 5-3 Diagram of input/output bus bars and terminal blocks (750kVA)

UPS module (750kVA)
Detailed Power Terminals
For power terminals, use 1/2" (12mm)
diameter bolts.
A
E
Grounding
Bar
B
AC Input
C
A 40
Bypass
B 40
Input
C 40
A 50
AC
B 50
Output
C 50
BP
DC Input
BN