Garmin G1000 Manual

Garmin G1000 Manual

Columbia 350/400 v8.xx software loading and post installation checkout
Hide thumbs Also See for G1000:
Table of Contents

Advertisement

Quick Links

G1000 V8.XX Software Loading
and Post Installation Checkout
Columbia 350/400
190-00577-04
June 2007
Revision 1

Advertisement

Table of Contents
loading

Summary of Contents for Garmin G1000

  • Page 1 G1000 V8.XX Software Loading and Post Installation Checkout Columbia 350/400 190-00577-04 June 2007 Revision 1...
  • Page 3 Garmin. Garmin hereby grants permission to download a single copy of this manual and of any revision to this manual onto a hard drive or other electronic storage medium to be viewed and...
  • Page 5 CAUTION All G1000 screen shots used in this document are current at the time of publication. Screen shots are intended to provide visual reference only. All information depicted in screen shots, including software file names, versions and part numbers, is subject to change and may not be up to date.
  • Page 6 (this page intentionally left blank) Page ii G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 7: Table Of Contents

    2.7.4 ChartView (if installed).......................... 2-19 2.7.5 Terrain/Obstacle/SafeTaxi Database Cards.................... 2-20 2.7.6 Aviation Database Loading........................2-21 Software/Configuration Troubleshooting....................2-22 2.8.1 System Communication Hierarchy ......................2-23 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page iii 190-00577-04 Revision 1...
  • Page 8 Site Evaluation of Magnetic Disturbances for Magnetometer Calibration Procedure (Optional)..3-31 3.12.2 GRS 77/GMU 44 Magnetic Calibration .................... 3-32 3.12.3 Engine Run-Up Vibration Test ......................3-34 3.12.4 Magnetometer Interference Test ......................3-36 Page iv G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 9 AFCS Switch Checks..........................4-2 Autopilot Clutch Overpower Check ......................4-3 Autopilot Disengagement Check ....................... 4-4 Manual Electric Trim Check........................4-4 Autopilot Operation Checks ........................4-4 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page v 190-00577-04 Revision 1...
  • Page 10 FIGURE 3-14. COM SETUP PAGE 3-49 FIGURE 3-15. GMA CONFIGURATION PAGE 3-50 FIGURE 4-1. GFC 700 PRE-FLIGHT TEST LIST OF TABLES TABLE PAGE TABLE 1-1. REFERENCED DOCUMENTATION....................1-1 Page vi G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 11: Introduction

    Columbia 400 unless noted otherwise. 1.2 Reference Documents The information that is provided in this document is applicable to the installation of the G1000 system in the Columbia 400. For additional information on the installation, refer to the documents below.
  • Page 12: Post Installation Process

    At the end, all software versions and part numbers are verified against the Required Equipment List (REL), Columbia Part Number RB011002. Section 3: Ground checks include exercising and testing basic G1000 functions, calibrating the AHRS, and conducting a final systems checkout. Section 4: Detailed GFC 700-specific ground checks are given in this section.
  • Page 13 The attitude indicator, airspeed indicator, altimeter and non-stabilized compass serve as secondary displays in the event of a failure of the associated primary indicator(s) and or sensors. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 1-3...
  • Page 14: G1000 System Communication

    GSA 81 GSA 81 GSA 81 Pitch Trim Adapter Pitch Trim Adapter Pitch Servo Pitch Servo Roll Servo Roll Servo Figure 1-1. G1000 System Interface Page 1-4 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 15: Figure 1-2. Eis Interface

    GRS 77 Integrated Integrated AHRS Avionics Unit Avionics Unit Attitude Rate of Turn Slip/Skid Output Output GMU 44 Magnetometer Heading Figure 1-3. Flight Instrumentation Interface G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 1-5 190-00577-04 Revision 1...
  • Page 16: G1000 Control Interface

    1.7 G1000 Control Interface Control and operation of G1000 equipment is through the PFD, MFD or GMA 1347 audio panel. See the following documents for detailed information regarding control and operation. G1000 Pilot’s Guide for Columbia 350/ 400, Garmin P/N 190-00552-00 Revision A or later.
  • Page 17: Fms Cursor

    1.7.1 FMS Cursor The FMS knob is the primary control for the G1000 system. Operation is similar to the Garmin 400/500 Series units. To cycle through different configuration screens: • To change page groups: Rotate the large FMS knob. To change pages in a group: Rotate the small FMS knob.
  • Page 18: Gma 1347 Control

    Figure 1-7. GMA 1347 Control Interface 1.7.5 Starting Configuration Mode To complete this aircraft checkout, a basic understanding of the G1000 configuration mode is required. The configuration mode allows a technician to access certain areas of the system in order to carry out various configurations, calibrations, and checks.
  • Page 19: Post Installation Procedures

    Before installing hardware, the technician must first ensure that hardware part numbers are compatible with the G1000-Columbia 400 Loader Card that is to be used. A G1000-Columbia 400 Loader Card is required to install software and configuration settings to a newly installed G1000 system. Should software part numbers or versions change, a new Loader Card part number is issued.
  • Page 20: G1000 Software/Configuration Procedure

    The following diagram depicts an overview of the software/configuration sequence for the G1000 system. If any problems are encountered during the loading process, see Section 2.8. It is extremely important that each LRU software load be completed successfully.
  • Page 21: System Power Up

    2.5.2 1. Pull the MFD and PFD circuit breakers. 2. Insert the correct G1000-Columbia 350/400 Loader Card into the MFD top card slot (refer to the Required Equipment List document for the correct card part number). 3. While holding the ENT key on the MFD, restore power by closing the MFD circuit breaker.
  • Page 22 9. New software is loaded to the MFD. When complete, the MFD starts in configuration mode. 10. Remove the G1000 Loader Card from the MFD and insert it into the top card slot on the PFD. Repeat Steps 3 through 7 for the PFD.
  • Page 23: G1000 System Software Upload

    Select the appropriate aircraft type (C400 or C350) and press the ENT key. IMPORTANT! Ensure that the correct airframe type is selected before proceeding; otherwise, incorrect configuration information will be loaded. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 2-5 190-00577-04 Revision 1...
  • Page 24 49 gallon (non-adjusted); 49 gallon (adjusted); 51 gallon (adjusted) and press ENT. IMPORTANT! It is at this step where the choice is given to load WAAS or non-WAAS G1000 software. Be sure to select the correct option. Page 2-6 G1000 V8.XX S/W Load and Post Install Checkout –...
  • Page 25 4. The PRODUCT window will populate and display software and configuration file information for each G1000 LRU. The LRU VERS column shows the currently loaded software version in the LRU, whereas the CARD VERS column shows the LRU software version stored on the Loader Card.
  • Page 26: Gia 63 Boot Block Update

    Take steps to ensure that a 28 VDC ground power supply is properly connected and is not disturbed during the update. 1. Obtain the required GIA 63 Boot Block loader card from Garmin. The card part number is listed in Table 1-1. Referenced Documentation 2.
  • Page 27 7. Verify that the SOFTWARE boxes are check for both GIA 1 and GIA 2. Press the LOAD softkey. 8. The GIA boot block software is loaded. Be sure not to remove electrical power from the G1000 during this update.
  • Page 28 10. The boot block update procedure is complete. Remove the GIA Boot Block loader card from the PFD and re-insert the correct G1000/GFC700 Software Loader card. Page 2-10 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 29: Software Load Confirmation

    GSA PTCH MON ___________ GFC CERT GIA1 ___________ GTA PTCH TRM ___________ GFC CERT GIA2 ___________ GSA ROLL CTL ___________ GTX1 ___________ GSA ROLL MON ___________ G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 2-11 190-00577-04 Revision 1...
  • Page 30: Final Configuration And Setup Items

    Troubleshoot and resolve the issue before continuing. 2.7 Final Configuration and Setup Items 2.7.1 Optional System Activation This section describes the steps that must be completed in order to configure the G1000 for optional systems. Only those systems that are installed must be configured. IMPORTANT...
  • Page 31 2.7.1.1 ADF (if installed) If the Columbia aircraft being updated is equipped with the Becker model RA3502 ADF (alternative KR87), follow this procedure to configure the G1000. If the aircraft is not equipped with this option, this procedure MUST be skipped.
  • Page 32 2.7.1.2 DME (if installed) If the Columbia aircraft being updated is equipped with the Honeywell model KN63 DME, follow this procedure to configure the G1000. If the aircraft is not equipped with this option, this procedure MUST be skipped. 1. At the System Upload page, activate cursor and rotate the FMS knob once to activate the AIRFRAME menu.
  • Page 33 6. View the SUMMARY field and ensure that all items are ‘complete’: Verify that PASS appears in green at the check box(es) as shown: 7. De-activate the cursor. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 2-15 190-00577-04...
  • Page 34 6. View the SUMMARY field and ensure that all items are ‘complete’: Verify that PASS appears in green at the check box(es) as shown: 7. De-activate the cursor. Page 2-16 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 35 6. View the SUMMARY field and ensure that all items are ‘complete’: Verify that PASS appears in green at the check box(es) as shown: 7. De-activate the cursor. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 2-17 190-00577-04...
  • Page 36: Aircraft Registration Number Entry

    4. Once the correct registration number is entered, press the ENT key. The transponder is configured: 5. The transponder then alerts the technician of complete configuration: 6. Press the ENT key on the PFD and deactivate the cursor. Page 2-18 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 37: Taws Activation (If Installed)

    2.7.3 TAWS Activation (if installed) Perform this procedure only if the aircraft is to be equipped with the Garmin TAWS option. 1. Remove power from the PFD by opening the PFD circuit breaker. 2. A special TAWS Unlock card is required to enable TAWS. Refer to the appropriate General Arrangement drawing for the correct part number.
  • Page 38: Terrain/Obstacle/Safetaxi Database Cards

    1. Remove power from the PFD and MFD using the respectively labeled breakers. NOTE: If the G1000 is to be equipped with the FliteChart or ChartView display options, the appropriate databases are required to be loaded onto the Terrain/Obstacle cards before they are installed in the displays.
  • Page 39: Aviation Database Loading

    2. Insert an aviation database update SD card into the top slot of the PFD. Database updates are supplied by Jeppesen. 3. Turn the G1000 system on. The following prompt is displayed in the upper left corner of the PFD: 4.
  • Page 40: Software/Configuration Troubleshooting

    • Check and ensure that correct Loader Card was used during load process. Refer to the Required Equipment List. • Reload software to LRU. Page 2-22 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 41: System Communication Hierarchy

    GIA2 configuration files. - GSA 81’s • Serial data path from GIA1 to each LRU must be operational. - GTA 82 - GCU 476 (configuration only) G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 2-23 190-00577-04 Revision 1...
  • Page 42: G1000 V8.Xx S/W Load And Post Install Checkout - Columbia

    This page intentionally left blank Page 2-24 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 43: System Testing & Checkout

    8. Set the flaps to UP and verify that the box for the FLAP RETRACT (IN 17) turns green while the flaps are retracting, and is black otherwise. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-1...
  • Page 44 13. Deactivate the cursor and then select the GFC STATUS page (2 page in GFC page group). The GIA 1 page for the Pitch Servo should be shown by default. Page 3-2 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 45 18. Activate the cursor and use the small FMS knob to highlight ROLL SERVO in the SELECT SERVO AXIS field and then press the ENT key. The ROLL SERVO GFC STATUS page will now be shown. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-3 190-00577-04...
  • Page 46 23. Activate the cursor and use the small FMS knob to highlight PITCH TRIM SERVO in the SELECT SERVO AXIS field and then press the ENT key. The PITCH TRIM SERVO GFC STATUS page will now be shown. Page 3-4 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 47 33. Move the trim switch on the copilot’s control stick to the TRIM DOWN position. Verify that the MANUAL TRIM CW box is green while the switch is in the TRIM DOWN position and is black otherwise. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-5 190-00577-04...
  • Page 48 37. Press the A/P DISC switch on the copilot’s control stick and verify that the green box in the GIA STATUS area is black while the A/P DISC switch is pressed. Page 3-6 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 49 40. Verify that the boxes beside the “4A L FUEL XFER PUMP SWITCH ON” (low fuel pressure) and “7A ENG 1 LOW OIL P” are green. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-7 190-00577-04...
  • Page 50: Carbon Monoxide Warning System

    3. Open the CO DETECTOR circuit breaker. Verify that the CO Guardian status changes to TIMEOUT after approximately five seconds. 4. Close the CO DETECTOR circuit breaker. Page 3-8 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 51: Stormscope (If Installed)

    3.1.3 WX-500 Stormscope (if installed) NOTE This procedure just verifies the WX-500 interface to the G1000. Other system checks must be carried out in accordance with the WX-500 Installation Manual. 1. Select the OTHER page group on the PFD. The STORMSCOPE page is shown by default.
  • Page 52: Ryan Tcad 9900Bx (If Installed)

    Audio Control Setting and Verification (TCAD volume must be set to 255) Weight on Wheels Verification (in the Columbia, this is connected to an airspeed switch) Page 3-10 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 53: Calibration And Activation

    4 4. Press the Elevator Trim RESET softkey (see Figure 3-1). Press ENT to acknowledge the following prompt after the RESET softkey is pressed: G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-11 190-00577-04...
  • Page 54: Fuel Quantity Transducer Calibration

    16. Calibration is complete. 3.2.2 Fuel Quantity Transducer Calibration NOTE The G1000 system can be calibrated for 49 as well as 51 gallon fuel tanks. Ensure the appropriate option has been selected when performing fuel calibration. Incorrect calibration will lead to misleading displays and potential fuel starvation of the aircraft.
  • Page 55 4. Start the G1000 system in Configuration mode. Reboot the MFD in normal mode for this procedure by pulling, then resetting, the MFD circuit breaker. On the MFD, press the ENGINE softkey to display the full page engine instrumentation. 5. Go to the CAL Page Group on the PFD. The FUEL TANK CALIBRATION page should be displayed as shown: 6.
  • Page 56 The calibrated value setting will default to 00.00. 4. Press the ENT key. A prompt appears requesting overwrite acknowledgement. Select YES and press the ENT key. The G1000 system will ‘zero’ the actual fuel quantity value to be displayed. 5. Select the RIGHT tank.
  • Page 57 6. In the table below, record the amount of usable fuel added to each tank. Also record the Calibration Value indications for both Right 1 and Left 1 Sub-Tanks. The amount of fuel added G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-15...
  • Page 58 The calibrated value setting will default to 49.00 or 51.00 as appropriate. 4. Press the ENT key. A prompt appears requesting overwrite acknowledgement. Select YES and press the ENT key. The G1000 system will set the actual fuel quantity value to be full. 5. Select the RIGHT tank.
  • Page 59: Initial Display Testing

    3.3 Initial Display Testing For the remainder of the system checkout procedures, the G1000 system is tested while operating in the normal mode unless otherwise specified. 1. Pull the MFD and PFD circuit breakers. 2. While holding the CLR key on the PFD, restore power by closing the PFD circuit breaker.
  • Page 60: Figure 3-3. Display Invalid Data Fields

    15. De-activate reversionary mode by pushing the GMA 1347 display backup button again. Page 3-18 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 61: Gps Signal Acquisition

    2. Apply heat to the area around the #1 EGT probe using a heat gun. Verify that the #1 cylinder EGT display shows the temperature increasing when the area around the sensor is heated. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-19...
  • Page 62: Tit Probes (C400 Only)

    PFD while the TEST button is pressed. Release the TEST button. NOTE The rudder limiter inhibit discrete output from the G1000 is active whenever MAP is below 12”Hg and cannot be tested as part of the ground check-out and consequently will have to be verified in a production test flight.
  • Page 63: Electrical Bus Voltages, Battery Currents And Alert Audio

    15. Close the INTEG AVION 2 circuit breaker and turn the RIGHT BAT master switch ON. 16. Turn the CROSS TIE switch ON. 17. Restore external power to the aircraft. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-21 190-00577-04...
  • Page 64: Cooling Fans

    5. Verify that the brightness of the bezel keys on the MFD is controlled by the two photocells on the MFD by covering the photocells and ensuring that the keys dim. Page 3-22 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 65 9. Return the UPPER dimmer switch to OFF (minimum brightness). NOTE If it is desired to further adjust the G1000 lighting characteristics, refer to section 3.18. 10. Slowly set the LOWER dimmer switch on the center console to maximum brightness.
  • Page 66: Gma 1347 Testing

    1. Using a ramp tester, simulate the outer marker, middle marker and inner marker signals by following the test equipment manufacturer’s instructions. Verify that each marker audio signal is present over the headphones and speaker. Page 3-24 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 67: Gia 63 Testing

    17. Repeat steps 14 through 16 for each of the following frequencies: 121.190 MHz • 130.285 MHz • 131.290 Mhz • 18. Repeat steps 13 through 17 for the No. 2 COM transceiver (GIA2). G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-25 190-00577-04 Revision 1...
  • Page 68: Vor/Loc/Gs Test

    Complete instructions for activating the XM data link can be found in document 190-00355-04. Page 3-26 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 69: Gtx 33 Testing

    3.8 GTX 33 Testing Operation of the GTX 33 Mode-S transponder is accomplished using the G1000 PFD. Refer to Garmin part number 190-00567-00, G1000 Cockpit Reference Guide for the Columbia 350/400, for basic operation.
  • Page 70: Oat Probe Check

    This procedure must be carried out with the engine off. Rotate the large FMS knob to select the GRS page group on the PFD. Rotate the small FMS knob clockwise to access the GRS/GMU calibration page on the PFD. Page 3-28 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 71: Engine Start

    To carry out the two remaining GRS/GMU procedures, the aircraft engine must be started. In order to start the engine, all engine/airframe transducers must have been checked to ensure proper operation. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-29...
  • Page 72: Figure 3-7. Engine/Airframe Indicators (Full Eis Page)

    R Battery Amps Negative if battery is discharging * Both GPU voltage with cross-tie closed (L L Bus Volts Both Battery volts when GPU disconnected) Page 3-30 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 73: Final Grs 77/Gmu 44 Calibration Procedures

    Magnetometer Calibration Procedure. A G1000-equipped Columbia 350/400 airplane can be used to evaluate a candidate site for magnetic disturbances and determine whether it is a suitable location to perform the magnetometer calibration procedure. The magnetometer calibration procedure itself contains the logic to simultaneously survey the location for magnetic cleanliness while it is computing the magnetometer calibration parameters.
  • Page 74: Grs 77/Gmu 44 Magnetic Calibration

    The G1000-equipped Columbia 350/400 used to evaluate the site must have already completed the pitch/roll offset compensation procedure (Procedure A). However, prior completion of the Magnetometer Calibration Procedure (Procedure B) is not required. In order to evaluate a candidate site, the Magnetometer Calibration Procedure must be performed twice: once turning clockwise around the site, and once turning counter-clockwise.
  • Page 75 Dwelling at these 30° increments for the time recommended by the PFD should result in successful calibration. 13. The PFD guides the operator to dwell at multiple headings around a complete circle. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-33 190-00577-04...
  • Page 76: Engine Run-Up Vibration Test

    3. The PFD display instructs the operator to gradually increase power from idle to full throttle and back to idle over a period of 1-2 minutes. Page 3-34 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 77 AHRS calibration, when the PFD powers up in normal mode, the AHRS attitude and heading information displayed should become valid within 1 minute of power-up. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-35 190-00577-04...
  • Page 78: Magnetometer Interference Test

    When the CALIBRATE field is blinking, press the ENT key to begin the procedure (as soon as the ENT key is pressed this time, a CALIBRATION PROCEDURE window will appear). Page 3-36 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 79: Figure 3-10. Magnetometer Interference Test Complete

    Z deviation greater than 8 mGauss after three attempts, then the installation should not be considered reliable until the source of the interference problem is identified and remedied. In the event of repeated failure of the magnetometer interference test, record G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-37 190-00577-04...
  • Page 80: Alternator Checks

    4. Press the MENU button and select “Test TAWS” from the pop-up menu and press ENT. 5. After the TAWS test has completed, verify that “TAWS System Test Okay” is heard over the cockpit speaker. Page 3-38 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 81: Optional System Checkouts

    This section describes the checks that must be completed in order to verify that optional systems are correctly configured and connected to the G1000. The checks must be completed only for those systems that are part of a particular installation. Optional systems are considered previously installed;...
  • Page 82: 9900 Bx Tcad (If Installed)

    3.15.2 9900 BX TCAD (if installed) NOTE If the G1000 has not received any ARINC 429 data from TCAD, the MUTE softkey will not be displayed. Instead, STBY, OPER and TEST softkeys will be displayed. 1. Select the TRAFFIC MAP map page on the MFD.
  • Page 83: Oxygen System (If Installed)

    6. Verify that the OXY OUTLET indicates between 16 and 33 psi. 7. Press the OXYGEN softkey on the MFD to turn off the oxygen flow. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-41 190-00577-04...
  • Page 84: Final System Checkout

    CO Detector Fail Stormscope Fail (if installed) TCAD Altitude Invalid (if installed) GMA 1 Fail (annunciation only) AHRS 1 Not Receiving GPS Info alert Page 3-42 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 85: Display Failure Test

    Air Data Computer. Engine Instrumentation flags invalid. 4. Restore power to the PFD and GIA2. All COM & NAV fields flag invalid. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-43 190-00577-04 Revision 1...
  • Page 86: Lighting Setup

    This section is for information only. Lighting data is loaded as part of the configuration upload. The lighting control system offers excellent configuration capability. During G1000 configuration, default lighting values are loaded. The following is only provided to allow for further refinement of the lighting system as determined by the technician.
  • Page 87: Figure 3-11. Main Lighting Page

    Keypad Lighting Adjustment Figure 3-11. Main Lighting Page Through configuration settings on this main lighting page, G1000 lighting can be setup and adjusted to suit each installation/cockpit environment. Each GDU must be configured for individual performance. The GMA 1347 audio panel and GCU 475/476 keypad lighting is also controlled from this page. Audio panel lighting is directly tied to display configuration, normally to the PFD (if the PFD fails, the MFD supplies lighting information to the GMA).
  • Page 88: Figure 3-12. Lighting Curve Vertices

    GAIN: Controls the brightness level of the arrow lights beneath the keys on the GMA. Range is between 0 and 2. Gain is a brightness multiplier and is best suited for small adjustments. Page 3-46 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 89: Cockpit Lighting Setup

    To accurately configure the lighting, the ability to adjust ambient light conditions is required. The installer should be prepared to simulating complete darkness in the G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-47 190-00577-04 Revision 1...
  • Page 90 If desired, set the photocell transition point and associated photo lighting curve to achieve desired display performance over a variety of lighting conditions. Page 3-48 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 91: Com Setup Page

    SQ 250: Sets the squelch threshold for 25 kHz channel spacing operation. May be set to any value between 0 (zero) and 63. The higher the number, the less signal is required to break squelch. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 3-49...
  • Page 92: Gma Configuration Page

    MIC GAIN: Sets the headset microphone gain level. May set to any value between 0 (zero) and 63. 3.20 GMA Configuration Page The GMA audio panel is configured as part of the G1000 system setup. The following is only provided to allow for further refinement of the marker beacon parameters as determined by the technician. No other settings should be adjusted.
  • Page 93: Gfc 700 Autopilot Ground Checks

    The following procedure will verify the proper operation of the GFC 700 AFCS. This procedure is designed to test the installation of the AFCS only after the G1000 testing in Section 3 has been conducted. The technician performing these checks must be thoroughly familiar with the GFC 700 by studying the following: Columbia 400 (G1000) Pilot’s Operating Handbook and FAA Approved AFMS, Columbia P/N...
  • Page 94: Afcs Switch Checks

    4. Actuate the MET switch forward/aft on the copilot’s control stick. The pitch trim should engage and the run in the selected direction. Check operation in both directions. Page 4-2 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...
  • Page 95: Autopilot Clutch Overpower Check

    When the system is on the ground, the electronic torque limiting is disabled, allowing manual checks of the slip-clutch settings. 1. Engage the Autopilot. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 4-3 190-00577-04...
  • Page 96: Autopilot Disengagement Check

    (as if the autopilot is disengaging) the servo actuator from that control axis should be removed and returned to Garmin (the servo mount does not have to be removed and replaced).
  • Page 97 PFD with an altitude reference equal to the aircraft altitude. 24. Press the FD key and verify that the mode annunciations and command bars are removed from the display. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Page 4-5 190-00577-04...
  • Page 98 The G1000 / GFC 700 configuration and ground testing is completed. The system is now ready for in- flight checks. Complete the information below. A copy of this procedure should be left with the aircraft records. Testing Completed By:_________________________________________ (Print Name)
  • Page 99 However, most protected pages are viewable to allow system awareness for troubleshooting. NOTE The OTHER page group will only be displayed if the G1000 is configured for the WX-500 Stormscope. G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400...
  • Page 100 1. Remote Controller Status 1. Fuel Calibration Page 2. Fuel Tank Calibration Page 3. Flaps and Trim Calibration Page G1000 Configuration Mode Page Navigator Page A-2 G1000 V8.XX S/W Load and Post Install Checkout – Columbia 350/400 Revision 1 190-00577-04...

Table of Contents