Trane Climate Changer T Series Installation Operation & Maintenance page 24

Table of Contents

Advertisement

Installation-Mechanical
Figure 5.
24
Never lift units in windy conditions. Personnel should be positioned overhead and on
the ground to guide the crane or helicopter operator in positioning the sections.
Never stack the pipe cabinet and inlet hoods on the unit as the unit is being lifted.
Do not attach the intake/exhaust hoods to the unit prior to lifting the unit. Doing so
may damage the equipment. Attach the hoods to the unit only after all sections are
in place.
Remove all wooden blocks before installing the unit to the roof curb. See
Shipping block removal
Remove all wooden blocks before
installing unit to roof curb
After the sections are in place, assemble the unit.
page
28.
See"Assembling the Unit" on
T-Series Climate Changer Air Handler IOM • CLCH-SVX06A-EN