Hand Over to Customer

6.1

Operational Steps

Important Points
a) The measurements taken during the test run should be recorded and kept on a test run inspection
b) Do not forget to record the length of the refrigerant piping and the refrigerant additional charging
c) Explain to the customer how to operate the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the system
e) Make the service contact address clear.
General Information
Make final report
Complete test run
(test run
inspection sheet)
sheet.
volume on the plate on the back of the outdoor unit external notice board, as this information will be
required for servicing the system.
and hand it all over to the customer (on the spot) and tell him to keep it.

Hand Over to Customer

Explain how to
Hand over
operate
relevant printed
equipment
materials
(V1050)
105