12. Operation
12.1 Operator's Working Position and
Operational Flow (Figure 12-1).
Once the box has been fi lled, close its top
fl aps and push it between the top and
bottom drive belts. Always keep hands
in position as shown in Figure 12-2.
The box will be automatically sealed with
adhesive tape on top and bottom box seams.
Box then fi nishes taping process and is released.
12.2 Starting the Machine
Important: Before starting the
machine, be sure no tools
or objects are on conveyor bed.
Let the machine run without cartons
and check its safety devices.
Then start the working cycle.
12.3 Starting Production
After adjusting machine to box dimensions
(height-width), let machine run without
cartons and check safety devices.
Then start working cycle.
12.4 Tape Replacement and Threading
See Manual 2: AccuGlide™ 4 Taping
Heads - 2 Inch or 3 Inch. Press the
LATCHING EMERGENCY STOP BUTTON.
12.5 Box Size Adjustment
Repeat all the operations shown in
Section 11 - Set-Up/Adjustments.
12.6 Cleaning
Before carrying out cleaning or
maintenance operation, stop the
machine by turning OFF (O) switch
on main and disconnect pneumatic
and electric power (Figure 12-3).
12.7 Table of Operation Adjustments -
Operator Qualifi cations
1 Tape loading and threading
2 Tape web alignment
3 Adjustment/one way tension roller 1
4 Adjustment to box size (H and W) 1
5 Top fl ap compression rollers
6 Adjustment of tape applying spring 1
7 Conveyor bed height adjustment 1
8 Special Adjust-Changing tape leg 2
9 Special Adjust-Column re-position 2
3M-Matic
7000r-7000r3 HS Pro - Type 11800
™
Page 45
44-0009-2152-6 / ECO# 0078045
Figure 12-1
-
-
Figure 10-1
Figure 12-3
"Reset" and
"Start-Stop"
1
1
Figure 12-4
1
12.8 Safety Devices Inspection
1. Taping units blade guard
2. Latching emergency stop button
3. STOP (OFF) (O) Button
Hand
Position
Figure 12-2
E-Stop
On
Off
Reset
North American - ENG
Date Released:
05-22-18