Site Preparation Checklist for QFX5120 Switches

The checklist in
Table 24 on page 65
installing a QFX5120 switch.
Table 24: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
switch tolerances.
Power
Measure the distance between external
power sources and the switch installation
site.
Locate sites to connect system grounding.
Calculate the power consumption and
requirements.
Hardware Configuration
Choose the number and types of switches
you want to install.
Rack or Cabinet
Verify that the rack meets the minimum
requirements for installing the switch.
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor and
building structure.
summarizes the tasks you need to perform to prepare a site for
For More Information
"Environmental Requirements and
Specifications for QFX5120
Switches" on page 66
"Clearance Requirements for
Airflow and Hardware
Maintenance for QFX5120
Switches" on page 71
AC Power Supply
Specifications for QFX5120
Switches on page 52
QFX5120 DC Power
Specifications on page 60
"QFX5120 Switches Hardware
Overview" on page 21
Rack Requirements for
QFX5120 Switches on page 69
Performed by
Date
65