Installing The Operating Unit And The Operating Add-On; Mounting And Wiring The Operating Unit - Siemens FS720 Mounting & Installation

Fire detection system
Table of Contents

Advertisement

Mounting and assembling a station
5

Installing the operating unit and the operating add-on

5.4 Installing the operating unit and the operating add-

5.4.1 Mounting and wiring the operating unit

42 | 222
Building Technologies
Fire Safety
on
This chapter describes how to assemble the operating units.
Prerequisites
The housing has been installed.
The operating unit options are fitted.
The procedure for mounting the operating unit in the Siemens wall housing is the
same for all operating units. The wiring differs according to which options are
installed. However, the cable routing is the same for all operating units.
From MP-EN 4.0 onwards, the operating units are supplied with the PMI &
mainboard FCM2027. Stations that are equipped with the PMI & mainboard
FCM2004 must not be integrated in an extended network. You will find detailed
information about this in product data document A6V10210368 and in the
planning document A6V10210362.
9
Figure 19: Mounting of the operating unit with PMI & mainboard FCM2027
1
2
3
8
7
6
4
5
5
A6V10210390_j_en_--
2015-12-15

Advertisement

Table of Contents
loading

Table of Contents