Wegaconcept
3
Machine installation
4
3
2
1
3.1
Positioning
Prepare an ample support base for the machine that
is suitable to support its weight (3).It is important for all
terminals of connections to the water mains (12) and to
the electrical mains (9) to be easily reachable and in any
case in the immediate vicinity of the machine.
Make sure that there is sufficient space for placing
and correctly using the appliance. The grinding-dosing
machine (4) must be placed in the immediate vicinity
of the appliance in order to allow for comfortable use
of the machine.
12
6
5
12
machine with a drawer (1) for used coffee grounds,
preferably with a rubber device (2) for tapping the filter
holder.
!
13
14
It is advisable to equip the working base of the
For correct operation, the machine must rest on a
perfectly horizontal surface. Any alignment of the
machine must be done by adjusting the feet (8).
7
8
9
10
11
15
Technical manual