Checklist A Procedures
A-2 Per form Pre- operation Ins pection
A-2
Perform Pre-operation Inspection
Genie specifications require that this procedure be
performed every 8 hours or daily, whichever
comes first.
Completing a Pre-operation Inspection is essential
to safe machine operation. The Pre-operation
Inspection is a visual inspection performed by the
operator prior to each work shift. The inspection is
designed to discover if anything is apparently
wrong with a machine before the operator
performs the function tests. The Pre-operation
Inspection also serves to determine if routine
maintenance procedures are required.
Complete information to perform this procedure is
available in the appropriate operator's manual.
Refer to the Operator's Manual on your machine.
20
A-3 Per form F uncti on Tes ts
A-3
Perform Function Tests
Genie specifications require that this procedure be
performed every 8 hours or daily, whichever
comes first.
Completing the function tests is essential to safe
machine operation. Function tests are designed to
discover any malfunctions before the machine is
put into service. A malfunctioning machine must
never be used. If malfunctions are discovered, the
machine must be tagged and removed from
service.
Complete information to perform this procedure is
available in the appropriate operator's manual.
Refer to the Operator's Manual on your machine.
GTH-1048 • GTH-1056