6.3

Load components from Project

Loading C300 Controller

Use the following general procedure to load a C300 Controller. The load procedure is
similar for all controller components.
Prerequisites
Control Builder is running
This procedure assumes that the C300 Controller is installed and capable of
communicating with the Server.
Considerations
Note that selecting a C300 Controller block for loading also selects the associated
CEEC300 block and IOLINK blocks.
All illustrations used in the procedure are for example purposes only.
To load a C300 Controller block and its associated blocks, perform the following steps.
Step
1
Click desired C300 block icon in Project
tab.
2
Click Tools > Load. Or, click the
load button in the toolbar.
Also, you can right click on the C300
block icon to select Load.
R500
April 2017
Action
Series 8 C300 Controller User's Guide
Honeywell
6. Load C300 Controller Configuration
6.3. Load components from Project
Result
Selects and highlights the component.
The Load Dialog box appears.