4. Connect the WAGO connectors to the I/O Board, referring to the interconnection
diagram.
5. Bind the cables to the fixing metal in the processor unit with the cable ties (sup-
plied).
Fixing metal
6. For the drain wire of the TTYCSLA series cable, attach shrink tubing (local supply)
to drain wire, fasten a crimp-on lug (pre-attached at location shown below) to drain
wire then fasten the wire with a screw.
Example of wiring inside the processor unit
Screws for drain wires
of TTYCSLA cables
Pass drain wire through shrink tubing (local
supply), attach a crimp-on lug (preattached)
to drain wire and fasten wire here.
J12 (main control unit)
For J13 and J14 (sub
control units), see the figure
at step 2 in this procedure.