7 Installation

7.12.11 Flues in voids

Especially for UK:
The flue system must be connected in accordance with the
manufacturers instructions before firing the boiler.
The term void includes ceiling voids, floor voids, purpose built
enclosures, service risers, roof spaces or any other enclosure that
will restrict access to inspect the flue.
To allow visual inspection, without reliance on devices such as
endoscopes, cameras and mirrors, inspection hatches must be
provided along the entire length of the flue.
Hatches must be a minimum of 300  mm×300  mm and positioned
with the edge of the inspection hatch to 1.5  m of any joint and at
changes of direction. Bends should be viewable from both directions
where the inspection hatch cannot be positioned at the bend.
Where suitable access is not provided the appliance must NOT be
commissioned and must be disconnected from the gas supply.
Additionally the entire flue and all flue seals must be installed in
accordance with the requirements of BS5440:
▪ Check if the condensate trap is filled with water and correctly
connected to the boiler.
▪ All flue joints are correctly made, unstressed and adequately
supported.
▪ All parts of the flue can be visually inspected. Ensure suitable
access where flue is positioned within voids.
7.13
Finishing the outdoor unit
installation
7.13.1

To finish the outdoor unit installation

7.13.2

To close the outdoor unit

See the outdoor unit installation manual.
7.14
Finishing the indoor unit
installation
7.14.1

To close the indoor unit

1 Close the switch box.
Installer reference guide
44
2 Mount the side plate to the unit.
3 Mount the top plate.
NOTICE
When closing the indoor unit cover, make sure that the
tightening torque does NOT exceed 4.1 N•m.
Before doing the configuration of the heat pump module, make sure
that the hybrid module and gas boiler are installed correctly.
7.15
Finishing the gas boiler
installation
7.15.1

To purge the gas supply

1 Turn once the screw counterclockwise.
Result: Gas supply will purge air.
2 Check all connections for leakage.
3 Check the gas supply pressure.
INFORMATION
Make sure the working inlet pressure does NOT interfere
with other gas appliances installed.
7.15.2

To close the gas boiler

1 Hook the top of the front panel into the top of the gas boiler.
Daikin hybrid for multi heat pump – heat pump module
CHYHBH05+08AA + EHYKOMB33A
4P471761-1A – 2017.10

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ehykomb33aChyhbh08aa

Table of Contents